Network Rail has announced that Carillion Powerlines Ltd has won the contract to deliver the electrification of the Shotts line between Holytown Junction and Midcalder Junction.
The GBP 49 million (EUR 56.5 million) contract will deliver 74 km of electrified railway, as part of a wider EUR 184.7 million Scottish Government investment in the line between Scotland’s largest cities.
The contract covers the physical delivery of all elements required to electrify the line, such as erecting stanchions and stringing the overhead powerlines, and will be carried out in tandem with work on a range of bridges as part of a route clearance programme to ensure the power cables can run under structures on the line.
Electric services will be introduced on Edinburgh-Glasgow Central via Shotts following completion of the work in 2019 and will offer improved reliability and increased capacity for passengers.