Consortia required to submit bids for Rail Baltica construction in Lativa

Latvia’s Rail Baltica line The development of requirements for the second stage of Latvia’s Rail Baltica mainline are completed and the qualified candidates are invited to submit technical and financial offers.

Candidates’ technical and financial proposals must be submitted by 31 October 2022. The procurement commission will select the technically and economically most advantageous proposal. The evaluation criteria for the technical proposal also include such parameters as reducing the environmental impact of the expected works, such as reduction of emissions generated by the construction machinery, use of reusable materials, etc., as well as a choice of solutions that ensure long service life.

Five construction companies are entering the second stage of the procurement process. The development of requirements for this stage has an extra complexity considering that the works included in the procurement foresee infrastructure construction of the Rail Baltica mainline on the territory of Latvia outside the borders of the city of Riga – the railway base and superstructure – over a length of 200 km.

The construction works include site preparation, embankment, construction of railway bridges, roads and overpasses, relocation of engineering networks and construction of tracks. Construction works will not only combine many complex construction elements but will also be the largest construction of railway infrastructure in Latvia.

Requirements of the tender include experience gained from the previously carried out tenders for the construction of the Rail Baltica Central Hub and the station and surrounding infrastructure at Riga International Airport, as well as from other Rail Baltica tenders being carried out in other Baltic countries.

Considering that final Rail Baltica construction designs are still under development and are therefore not fully completed before the announcement of procurement’s 2nd stage, Eiropas Dzelzceļa līnijas will apply the so-called re-measurement contract mechanism instead of lumpsum allowing that payments are made according to the volumes of the completed works, using unit prices and preventing overpayments. Also, based on the internationally spread early involvement method, the construction company will be involved already in the design phase.

Requirements for the candidates are defined both for the starting and carrying out of the construction works, as well as for the commissioning of the infrastructure after several years of construction, demonstrating a long-term view on how the operations of the newly built railway could be started. In view of changing prices in the construction sector, an indexation mechanism is foreseen, which, given the current situation with material prices, will enable the contracting authority to avoid risks related to price fluctuation.

The construction of Latvia’s Rail Baltica mainline is expected to start in 2023 beginning with works outside Riga after the approval of construction designs of the specific stages.

Construction works will be carried out in a priority manner, from Riga Airport to the Lithuanian border and from the Salaspils intermodal freight terminal towards the direction of Lithuania. By implementing such a construction strategy, the European gauge connection will initially provide rail access to Riga Airport and the Salaspils terminal, ensuring a connection with to Estonia in the next stage.

The first construction works are planned in Bauska Municipality near Iecava, where the future Rail Baltica infrastructure maintenance facility will be located

 