Bombardier-Alstom-Indra consortium wins control contract for Madrid-Lisbon HSR

ertms_spainSpain’s Administrator of Railway Infrastructure (ADIF) awarded Bombardier- Alstom – Indra consortium a EUR 164 million contract on the supply on signalling systems and maintenance services for the new high-speed section of the Madrid- Lisbon.
Bombardier’s share is valued at approximately EUR 77 million, Alstom’s share is valued at approximately EUR 62 million, and Indra’s share is approximately EUR 25 million.
The Bombardier-led consortium will deliver the design, procurement, installation, testing and commissioning of the signalling and communication systems. This includes ERTMS Level 2  installing on the 164 km Plasencia-Cáceres and Cáceres-Badajoz sections of the line.
The project also includes a 20 year maintenance regime to commence at the end of phase one of the signalling system delivery. Bombardier will implement its proven, radio-based BOMBARDIER INTERFLO 450 ERTMS Level 2 solution for the entire line.
Alstom is responsible for the electronic interlocking system and will supply the reliable and proven Smartlock 300 solution, and Indra will implement the Spanish automatic train protection (ASFA) system.