Major milestone for Thames Valley electrification

Network Rail has completed the electrification of 19 km railway to the west of London between Stockley Junction and Maidenhead as part of the Crossrail project.
Electrification will allow Great Western Railway (GWR) to extend new electric trains from London Paddington to Maidenhead from this May, and to Didcot in January 2018, delivering more seats for passengers. In January this year GWR began to run half-hourly new Electrostar trains from London Paddington to Hayes & Harlington, providing much needed extra capacity for passengers.
The work will also allow for the delivery of new Elizabeth line trains on this section of the railway from December 2019. Passengers in the Thames Valley will be able to catch new Elizabeth line trains all the way through central London without having to change onto the Underground at Paddington, making it quicker and easier to get to a range of destinations across London and the South East.
“The completion of this major piece of work paves the way for new, quicker, quieter trains right along this stretch of the railway. Once the Elizabeth line opens fully in 2019, passengers from the Thames Valley will be able to catch one train all the way through central London, providing a direct link to a range of destinations, including the West End, the City and Canary Wharf,” Matthew White, Crossrail Surface Director, said.


Share on:
Facebooktwitterlinkedinmail

 

RECOMMENDED EVENT: